Log in

Scorecard Inbound

Export August 2025

Counts the AppSheet inbound POs of the scored locations whose Unloading_TS is in August 2025. The clock runs from Unloading (Unloading_TS) to GR (GR_TS); Reguler = SCM - Type PO Regular, Gimmick = every other type.

Scorecard Inbound Summary

Unloading → GR within 16 h for Reguler POs, 72 h for every other type (Gimmick) · Remark % = (on time + late with a remark) ÷ total

Summary
Total OnTimeLateRemark
36 8 28 0
% 22.22% 77.78% 22.22%
KPI 99.50% 0.50% 99.50%
Reguler
Total Reg OnTimeReg LateReg Remark
22 4 18 0
% 18.18% 81.82% 18.18%
KPI 99.50% 0.50% 99.50%
Gimmick
Total Gim OnTimeGim LateGim Remark
14 4 10 0
% 28.57% 71.43% 28.57%
KPI 99.50% 0.50% 99.50%

Scorecard Inbound Detail

PO Vendor / location Type Unloading → GR Durasi / SLA Remark
PO/KNS/2025/000014766
PT. Unza Vitalis
Wipro Unza
Gimmick
Unload 30/08 10:37
Finish 30/08 11:03
GR 30/08 17:26
6:49:20 / 72 h
On time
—
PO/KNS/2025/000014765
PT. Unza Vitalis
Wipro Unza
Reguler
Unload 30/08 10:37
Finish 30/08 11:03
GR 30/08 16:57
6:20:11 / 16 h
On time
—
PO/KNS/2025/000014764
PT. Unza Vitalis
Wipro Unza
Reguler
Unload 30/08 10:36
Finish 30/08 11:02
GR 30/08 16:57
6:21:21 / 16 h
On time
—
PO/KNS/2025/000014816
PT. Unza Vitalis
Wipro Unza
Reguler
Unload 30/08 09:20
Finish 30/08 10:31
GR 30/08 16:57
7:37:13 / 16 h
On time
—
PO/KNS/2025/000012107
PT. NESTLE INDONESIA
Purina
Gimmick
Unload 29/08 13:28
Finish 29/08 13:28
GR 29/08 13:38
0:09:55 / 72 h
On time
—
PO/KNS/2025/000014516
PT. Tigaraksa Satria Tbk
Purina
Reguler
Unload 27/08 10:08
Finish 27/08 12:08
GR 01/09 15:46
125:37:40 / 16 h
Late · 109:37:40
Needs remark
PO/KNS/2025/000014515
PT. Tigaraksa Satria Tbk
Purina
Reguler
Unload 27/08 10:08
Finish 27/08 15:04
GR 28/08 17:11
31:03:13 / 16 h
Late · 15:03:13
Needs remark
PO/KNS/2025/000012927
PT. Tigaraksa Satria Tbk
Purina
Gimmick
Internal
Unload 26/08 17:28
Finish 26/08 17:28
GR 29/08 13:38
68:10:27 / 72 h
On time
—
PO/KNS/2025/000014069
PT. Unza Vitalis
Wipro Unza
Reguler
Unload 22/08 14:41
Finish 22/08 15:59
GR 25/08 11:18
68:37:00 / 16 h
Late · 52:37:00
Needs remark
PO/KNS/2025/000014070
PT. Unza Vitalis
Wipro Unza
Gimmick
Unload 22/08 14:36
Finish 22/08 14:37
GR 26/08 14:52
96:15:39 / 72 h
Late · 24:15:39
Needs remark
36 total
Prev 1 / 4 Next