Scorecard Outbound

Calculated 03 Nov, 04:07 · Refresh

Export September 2026

Counts delivery orders with status Done whose order date (order_tstamp) is in September 2026. The clock runs from OP (op_timestamp) to OB (ob_timestamp); Instant = Instant / Same Day couriers, Regular = the rest.

Scorecard Outbound Summary

Regular: before 17:00:00 (Mon–Sat) → OB by 23:59:59 the same day · Instant: before 15:00:00 → OB within 3 h (+1 h lunch) from max(OP, 09:00:00) · Remark % = (on time + late with a remark) ÷ total

Remark counts as OK:

Scorecard Outbound Detail

  • WHKUN/OUT/31601

    Unilever Nutritions

    Regular

    585997951830755250 · GTL7236397676 · GTL - Reguler

    Order 10/09 16:01 · OP 10/09 16:18 · OB 11/09 06:48

    by 10/09 23:59
    Late · 6:48:56
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
  • WHKUN/OUT/31600

    Unilever Nutritions

    Regular

    585997889561003836 · GTL7209317786 · GTL - Reguler - COD

    Order 10/09 16:01 · OP 10/09 16:18 · OB 11/09 05:07

    by 10/09 23:59
    Late · 5:07:05
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
  • WHKUN/OUT/31604

    Unilever Nutritions

    Regular

    585997925648926293 · 570597635111 · J&T Cargo - COD

    Order 10/09 16:01 · OP 10/09 16:18 · OB 11/09 05:07

    by 10/09 23:59
    Late · 5:07:07
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
  • WHKUN/OUT/31618

    Unilever Nutritions

    Regular

    585997903623063047 · 002975903687 · SiCepat - Reguler

    Order 10/09 16:01 · OP 10/09 16:19 · OB 11/09 08:20

    by 10/09 23:59
    Late · 8:20:37
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
  • WHKUN/OUT/31603

    Unilever Nutritions

    Regular

    585997932316034766 · 570596956447 · J&T Cargo - COD

    Order 10/09 16:00 · OP 10/09 16:18 · OB 11/09 08:20

    by 10/09 23:59
    Late · 8:20:40
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
4015 total
Prev 159 / 803 Next

Scorecard Outbound Issue

No Tanggal Issue Lampiran
1 09 Sept 2026 Pada pelaksanaan event Twin Date 9.9, terjadi peningkatan actual order yang cukup signifikan dibandingkan forecast yang di sampaikan pada saaat Metting preperation. Kondisi over forecast ini menyebabkan beban kerja aktual melebihi kapasitas yang telah direncanakan. Manpower yang disiapkan berdasarkan forecast awal menjadi tidak mencukupi, sehingga proses operasional mengalami keterlambatan (late).
[SFKE00003] ARI WIBOWO