Counts delivery orders with status Done whose order date (order_tstamp) is in September 2026. The clock runs from OP (op_timestamp) to OB (ob_timestamp); Instant = Instant / Same Day couriers, Regular = the rest.
Scorecard Outbound Summary
Regular: before 17:00:00 (Mon–Sat) → OB by 23:59:59 the same day · Instant: before 15:00:00 → OB within 3 h (+1 h lunch) from max(OP, 09:00:00) · Remark % = (on time + late with a remark) ÷ total
Scorecard Outbound Detail
| DO | Reference | Type | Order → OP → OB | SLA | Remark |
|---|---|---|---|---|---|
|
WHKUN/OUT/30810
Unilever Nutritions
|
585996126344152877
JY1680275916
|
Regular J&T - Express - COD
|
Order 10/09 13:56
OP 10/09 14:05
OB 11/09 23:47
|
by 10/09 23:59
Late · 23:47:33
|
Over forecast
ORDERAN OVER FORCASE CUTTOFF JAM 3
|
|
WHKUN/OUT/30813
Unilever Nutritions
|
585996267133502893
JY1671955296
|
Regular J&T - Express - COD
|
Order 10/09 13:56
OP 10/09 14:05
OB 11/09 01:21
|
by 10/09 23:59
Late · 1:21:36
|
Over forecast
ORDERAN OVER FORCASE CUTTOFF JAM 3
|
|
WHKUN/OUT/30803
Unilever Nutritions
|
585996236613125374
JY1609885896
|
Regular J&T - Express - COD
|
Order 10/09 13:55
OP 10/09 14:05
OB 11/09 02:06
|
by 10/09 23:59
Late · 2:06:47
|
Over forecast
ORDERAN OVER FORCASE CUTTOFF JAM 3
|
|
WHKUN/OUT/30800
Unilever Nutritions
|
585996263855720166
JY1676815286
|
Regular J&T - Express - COD
|
Order 10/09 13:55
OP 10/09 14:04
OB 11/09 03:19
|
by 10/09 23:59
Late · 3:19:44
|
Over forecast
ORDERAN OVER FORCASE CUTTOFF JAM 3
|
|
WHKUN/OUT/30804
Unilever Nutritions
|
585996222919968197
002975649884
|
Regular SiCepat - Reguler
|
Order 10/09 13:55
OP 10/09 14:05
OB 11/09 03:24
|
by 10/09 23:59
Late · 3:24:09
|
Over forecast
ORDERAN OVER FORCASE CUTTOFF JAM 3
|
-
WHKUN/OUT/30810
Unilever Nutritions
Regular585996126344152877 · JY1680275916 · J&T - Express - COD
Order 10/09 13:56 · OP 10/09 14:05 · OB 11/09 23:47
by 10/09 23:59Late · 23:47:33Over forecastORDERAN OVER FORCASE CUTTOFF JAM 3 -
WHKUN/OUT/30813
Unilever Nutritions
Regular585996267133502893 · JY1671955296 · J&T - Express - COD
Order 10/09 13:56 · OP 10/09 14:05 · OB 11/09 01:21
by 10/09 23:59Late · 1:21:36Over forecastORDERAN OVER FORCASE CUTTOFF JAM 3 -
WHKUN/OUT/30803
Unilever Nutritions
Regular585996236613125374 · JY1609885896 · J&T - Express - COD
Order 10/09 13:55 · OP 10/09 14:05 · OB 11/09 02:06
by 10/09 23:59Late · 2:06:47Over forecastORDERAN OVER FORCASE CUTTOFF JAM 3 -
WHKUN/OUT/30800
Unilever Nutritions
Regular585996263855720166 · JY1676815286 · J&T - Express - COD
Order 10/09 13:55 · OP 10/09 14:04 · OB 11/09 03:19
by 10/09 23:59Late · 3:19:44Over forecastORDERAN OVER FORCASE CUTTOFF JAM 3 -
WHKUN/OUT/30804
Unilever Nutritions
Regular585996222919968197 · 002975649884 · SiCepat - Reguler
Order 10/09 13:55 · OP 10/09 14:05 · OB 11/09 03:24
by 10/09 23:59Late · 3:24:09Over forecastORDERAN OVER FORCASE CUTTOFF JAM 3
Detail
Scorecard Outbound Issue
| No | Tanggal | Issue | Lampiran |
|---|---|---|---|
| 1 | 09 Sept 2026 | Pada pelaksanaan event Twin Date 9.9, terjadi peningkatan actual order yang cukup signifikan dibandingkan forecast yang di sampaikan pada saaat Metting preperation.
Kondisi over forecast ini menyebabkan beban kerja aktual melebihi kapasitas yang telah direncanakan. Manpower yang disiapkan berdasarkan forecast awal menjadi tidak mencukupi, sehingga proses operasional mengalami keterlambatan (late). [SFKE00003] ARI WIBOWO |