Scorecard Outbound

Calculated 09 Nov, 13:18 · Refresh

Export September 2026

Counts delivery orders with status Done whose order date (order_tstamp) is in September 2026. The clock runs from OP (op_timestamp) to OB (ob_timestamp); Instant = Instant / Same Day couriers, Regular = the rest.

Scorecard Outbound Summary

Regular: before 17:00:00 (Mon–Sat) → OB by 23:59:59 the same day · Instant: before 15:00:00 → OB within 3 h (+1 h lunch) from max(OP, 09:00:00) · Remark % = (on time + late with a remark) ÷ total

Remark counts as OK:

Scorecard Outbound Detail

  • WHKUN/OUT/26986

    Unilever Nutritions

    Regular

    585982822028642136 · JY1658366765 · J&T - Express - COD

    Order 09/09 19:40 · OP 09/09 20:17 · OB 11/09 02:45

    by 10/09 23:59
    Late · 2:45:23
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
  • WHKUN/OUT/26900

    Unilever Nutritions

    Regular

    585982676689651488 · JY1641257275 · J&T - Express - COD

    Order 09/09 19:29 · OP 09/09 19:50 · OB 11/09 03:09

    by 10/09 23:59
    Late · 3:09:42
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
  • WHKUN/OUT/31627

    Unilever Nutritions

    Regular

    585982447629600078 · 570597599319 · J&T Cargo

    Order 09/09 19:25 · OP 10/09 16:20 · OB 11/09 08:05

    by 10/09 23:59
    Late · 8:05:29
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
  • WHKPR/OUT/100856

    Purina Official Store

    Regular

    260909K2P4BWUU · 11004355452725 · AnterAja - Economy

    Order 09/09 19:22 · OP 10/09 15:49 · OB 11/09 13:44

    by 10/09 23:59
    Late · 13:44:54
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
  • WHKUN/OUT/26822

    Unilever Nutritions

    Regular

    585982305953089198 · 002975340670 · SiCepat - Reguler

    Order 09/09 19:16 · OP 09/09 19:36 · OB 11/09 01:55

    by 10/09 23:59
    Late · 1:55:24
    Over forecast
    ORDERAN OVER FORCASE CUTTOFF JAM 3
4015 total
Prev 368 / 803 Next

Scorecard Outbound Issue

No Tanggal Issue Lampiran
1 09 Sept 2026 Pada pelaksanaan event Twin Date 9.9, terjadi peningkatan actual order yang cukup signifikan dibandingkan forecast yang di sampaikan pada saaat Metting preperation. Kondisi over forecast ini menyebabkan beban kerja aktual melebihi kapasitas yang telah direncanakan. Manpower yang disiapkan berdasarkan forecast awal menjadi tidak mencukupi, sehingga proses operasional mengalami keterlambatan (late).
[SFKE00003] ARI WIBOWO